Great job to the Belmont Crew for a successful 24-hour shutdown on the Belmont Grit & Screenings Conveyor Project. The crew demolished an existing conveyor and installed a new 110 foot long 36” wide conveyor within a 24-hour period while under live flow and without interruption of the normal plant operation. The culmination of months of planning resulted in a successful installation. Many thanks to the crew and everyone who assisted in the planning process and execution.